January 6
Rebar/Steel Belly Day!
January 11
It rained and part of the wall collapsed.
January 12
Gunite Day!
January 14
January 15
Tile Day
January 21
We had three different crews working on the pool at the same time! Plumbers, masons, and the men building the new arbor and porch.
January 29
The shingles go on the roof of the "cabana"